ZAP Engineering EPC LNG liquefaction, storage, and truck loadout facility — Massachusetts

LNG

EPC Delivery of an LNG Liquefaction & Storage Facility

Full turnkey EPC delivery of a greenfield natural gas liquefaction, storage, and truck-loadout facility in Massachusetts, from engineering through startup and handover.

Project Overview

ZAP was engaged by an LNG developer to deliver a full turnkey EPC scope — engineering, procurement, construction, and start-up and commissioning through handover — for a greenfield natural gas liquefaction, storage, and truck-loadout facility in Massachusetts. The facility takes pipeline natural gas from two existing interstate laterals, pretreats it, liquefies it, stores it, and dispenses LNG to trucks, with a design inlet flow up to 24 MMSCFD and a production capacity of 250,000 gallons of LNG per day.

Gas Treatment & Liquefaction Process

Inlet gas is treated in an amine unit to remove carbon dioxide and hydrogen sulfide, then dried in a two-bed molecular sieve dehydration unit before entering a liquefaction cold box that liquefies the gas to approximately minus 260 degrees Fahrenheit using a nitrogen refrigeration cycle driven by a gas turbine. Boil-off gas from storage and truck loading is recovered and recycled back into the process rather than flared or vented.

LNG Storage & Automated Truck Loading

LNG is stored in a vertical, double-wall, full-containment 2-million-gallon tank with a stainless steel inner tank and a precast, prestressed-concrete outer wall serving as secondary containment. LNG is delivered to trucks through in-tank loading pumps and vacuum-jacketed piping across three fully automated loading bays equipped with truck scales.

Electrical Systems & Cryogenic Design Challenges

ZAP’s electrical scope included a utility interconnect, a main transformer, medium-voltage switchgear paralleled with turbine-driven generation, a boil-off-gas-fired backup generator, and an Allen-Bradley control and safety system with a ZAP-supplied fire-and-gas system and custody-transfer metering. Key technical challenges centered on cryogenic service requiring stainless steel, 9% nickel steel, and low-temperature piping classes, staged cold-box cooldown, hazardous-area electrical classification, and a demanding regulatory basis including federal LNG regulations, NFPA 59A, and state requirements.

Client

LNG Liquefaction & Storage Developer

Market

Energy & Chemicals

Location

Massachusetts

Services

  • EPC Project Delivery
  • Detailed Engineering & Design
  • Procurement
  • Construction
  • Commissioning & Start Up Support

Engineering Disciplines

  • Process/Chemical
  • Mechanical
  • Civil
  • Structural
  • Electrical
  • Instrumentation & Controls

Shane Wilson

Vice President of Business Development


Contact us

We partner with clients across the energy and industrial markets to solve complex technical challenges and deliver projects that perform.