Distribution Terminals
ZAP performed front end engineering and cost estimation before completing the detailed engineering, procurement and construction planning for a 40,000 BPD crude stabilization facility.
Distribution Terminals
ZAP was contracted to complete a total installed cost estimate for the addition of two crude oil storage tanks and associated equipment required for metering at an existing crude oil terminal.
Distribution Terminals
ZAP completed the process, mechanical, structural engineering and design for the addition of a 100,000 BBL tank to an existing crude oil terminal.
Distribution Terminals
ZAP provided support with upgrading an existing frac sand terminal for fly-ash handling.
Distribution Terminals
ZAP was responsible for the mechanical, civil, structural and electrical design for the upgrade of a terminal in Henderson, Colorado.
Distribution Terminals
ZAP provided preliminary engineering and design for a cement and granulated blast furnace slag import and distribution terminal.
Distribution Terminals
ZAP completed detailed engineering to replace the existing reclaim belts and airslides at a cement terminal.
Distribution Terminals
ZAP was contracted to perform conceptual layout, design and total installed cost estimate for a new pneumatic truck off-loading, storage and automated truck loading system.
Distribution Terminals
ZAP was contracted by our client to perform conceptual layout and design for a new rail distribution terminal. The system was designed to receive cement by dual rail tracks and off-load simultaneously into one of four silos.
Pipeline
Pig Launcher Modifications, Regulator Install, and IA Addition ZAP Engineering completed design work on modifying the piping of an existing pig launcher to accommodate the addition of a regulator skid, and instrument air building at a site located in the pipeline ROW.
Pipeline
Meter Skid and Pig Valve Skid Installation ZAP Engineering completed design work for the installation of a new meter skid and pig valve skid at a third party site.
Pipeline
Filter, Meter Skid and Control Valve Skid Installation ZAP Engineering completed design work for the installation of a new filter coalescer, meter skid, and control valve skid at a third party interconnect site. Scope included specifying the equipment, and preparing a complete construction drawing package.
Cement, Mining, and Minerals
Preheater Evaluation A cement plant was seeking to upgrade the size of the cyclones in their Preheater Tower which was going to modify both the framing geometry and maximum expected gravity and seismic loads on the tower. A structural & construction evaluation was required to provide a total installed cost and schedule estimates for their […]
Cement, Mining, and Minerals
TDF Electrical and Instrumentation A cement plant improving the efficiency of their alternate fuel sources requested that ZAP provide electrical and instrumentation design to support the integration of equipment packages into a single material handling system. The new system would allow for the delivery of whole tires that would be shredded prior to being used […]